Search Pass4Sure

PMP Exam Formula Sheet: All Key Calculations

Complete PMP exam formula sheet with all EVM formulas, PERT calculations, communication channels, EMV, and schedule variance formulas with worked examples.

PMP Exam Formula Sheet: All Key Calculations

What formulas do I need to know for the PMP exam?

The PMP exam tests Earned Value Management formulas most frequently: EV (Earned Value = BAC x % Complete), CV (Cost Variance = EV - AC), SV (Schedule Variance = EV - PV), CPI (Cost Performance Index = EV/AC), SPI (Schedule Performance Index = EV/PV), EAC (Estimate at Completion = BAC/CPI), and ETC (Estimate to Complete = EAC - AC). These formulas appear in numerical scenario questions and must be applied under time pressure.


The PMP exam contains approximately 15-20 quantitative questions that require applying formulas to project scenarios. While the current exam is scenario-heavy and tests judgment more than calculation, earned value management (EVM) calculations and project schedule formulas remain testable content that candidates must master.

The mistake most PMP candidates make is treating formulas as an afterthought. EVM questions reward precision: confusing EAC with ETC or misremembering whether a positive CPI means over or under budget can cost two to three questions. This formula sheet is designed for regular review in the final month before the exam.


Earned Value Management (EVM) Formulas

Foundation Values

Term Abbreviation Definition How to Calculate
Budget at Completion BAC Total authorized budget for work Given in question
Planned Value PV Authorized budget for work scheduled to be done by now Given or calculated from schedule
Earned Value EV Value of work actually completed to date BAC x % Complete
Actual Cost AC Actual cost incurred for work done to date Given in question

"Earned Value is not what you spent. It is the budgeted cost of the work you completed. Confusing EV with AC is the single most common calculation error on PMP exams." -- PMP preparation instructor

Variance Formulas

Metric Formula Positive = Good Negative = Bad
Cost Variance (CV) EV - AC Under budget Over budget
Schedule Variance (SV) EV - PV Ahead of schedule Behind schedule
Cost Performance Index (CPI) EV / AC > 1 = under budget < 1 = over budget
Schedule Performance Index (SPI) EV / PV > 1 = ahead of schedule < 1 = behind schedule
To-Complete Performance Index (TCPI) (BAC - EV) / (BAC - AC) < 1 = achievable > 1 = aggressive

Memory trick for CV and SV: "Earned first" -- EV is always the first term subtracted. CV = EV - AC, SV = EV - PV.

Forecasting Formulas

Metric Formula When to Use
EAC (assume CPI continues) BAC / CPI When current performance trend is expected to continue
EAC (assume remaining work on budget) AC + (BAC - EV) When remaining work will be done at original estimate
EAC (new estimate) AC + ETC When original estimate is no longer valid, use new estimate for remaining work
ETC (typical) EAC - AC Remaining work to complete at current performance
VAC (Variance at Completion) BAC - EAC Projected final overrun (negative) or underrun (positive)

Schedule and Duration Formulas

PERT (Program Evaluation and Review Technique)

Three-point estimate (PERT Beta distribution):

PERT Estimate = (Optimistic + 4 x Most Likely + Pessimistic) / 6

PERT Standard Deviation:

Standard Deviation = (Pessimistic - Optimistic) / 6

PERT Variance:

Variance = Standard Deviation squared = [(Pessimistic - Optimistic) / 6]^2

Example: Task with O=2, ML=5, P=14

  • PERT = (2 + 4x5 + 14) / 6 = (2 + 20 + 14) / 6 = 36/6 = 6 days
  • SD = (14 - 2) / 6 = 12/6 = 2 days
  • 68% confidence: 6 +/- 2 = 4 to 8 days
  • 95% confidence: 6 +/- 4 = 2 to 10 days
  • 99.7% confidence: 6 +/- 6 = 0 to 12 days

Triangular Distribution (Simpler Alternative)

Triangular Estimate = (Optimistic + Most Likely + Pessimistic) / 3


Communication and Stakeholder Formulas

Communication Channels

Formula: n(n-1)/2 where n = number of stakeholders

Stakeholders Communication Channels
2 1
5 10
10 45
15 105
20 190

Exam application: If project grows from 10 to 15 team members, new channels added = 105 - 45 = 60 additional channels.


Probability and Expected Monetary Value

Expected Monetary Value (EMV)

EMV = Probability x Impact

Used in decision tree analysis and risk reserve calculations.

Example:

  • Risk A: 30% probability of $10,000 loss = -$3,000 EMV
  • Risk B: 20% probability of $5,000 gain = +$1,000 EMV
  • Net EMV = -$3,000 + $1,000 = -$2,000 (negative = net risk exposure)

Contingency Reserve

Contingency reserve is typically calculated as the sum of EMVs for identified risks, adjusted by risk appetite.


Float and Critical Path Concepts

Float (Total Float): Latest Finish - Earliest Finish, OR Latest Start - Earliest Start

Free Float: How much an activity can slip without affecting the early start of successor activities.

Critical Path: Sequence of activities with zero float from project start to finish.

Schedule Network Analysis formulas:

  • Early Finish (EF) = Early Start (ES) + Duration - 1
  • Late Start (LS) = Late Finish (LF) - Duration + 1
  • Total Float = LS - ES OR LF - EF

"The critical path is not always the longest path in days. It is the path with zero float. In some network diagrams these are the same; in others with mandatory lags they can differ." -- PMP preparation course instruction


Process Improvement Formulas

Quality and Control Charts

Mean (Average): Sum of all values / Number of values

Standard Deviation: Indicates spread of data around mean

Control chart limits:

  • +/- 1 sigma (standard deviation): 68.27% of data points
  • +/- 2 sigma: 95.45% of data points
  • +/- 3 sigma: 99.73% of data points

Rule of Seven: Seven consecutive data points on the same side of the mean indicates the process is out of control, even if all points are within control limits.


PMP Formula Quick Reference Card

Formula Full Expression
EV BAC x % Complete
CV EV - AC
SV EV - PV
CPI EV / AC
SPI EV / PV
EAC BAC / CPI
ETC EAC - AC
VAC BAC - EAC
TCPI (BAC - EV) / (BAC - AC)
PERT (O + 4ML + P) / 6
SD (P - O) / 6
Comm channels n(n-1) / 2
EMV Probability x Impact

Frequently Asked Questions

How many formula questions are on the PMP exam? The current PMP exam contains approximately 15-20 quantitative questions out of 180 total. This represents roughly 10% of the exam. While formulas are not the majority of the test, getting all formula questions right adds meaningful points, and the EVM calculation sequence is predictable and fully preparable.

Do I need to memorize all EVM formulas or will they be provided? EVM formulas are not provided during the PMP exam. You must memorize them. The exam does provide scratch paper (erasable notepad), and most candidates immediately write down all formulas before reading the first question. Practice writing the full formula set from memory in under two minutes.

Is the PERT formula always tested or just sometimes? PERT three-point estimates appear on the PMP exam with some regularity. Candidates occasionally encounter questions requiring them to calculate the PERT estimate and standard deviation for an activity and then determine the probability range. Know both the PERT beta formula and the triangular distribution formula, as questions sometimes specify which to use.

References

  1. Project Management Institute. (2021). A Guide to the Project Management Body of Knowledge (PMBOK Guide) -- Seventh Edition. PMI.
  2. Project Management Institute. (2021). Practice Standard for Earned Value Management, Third Edition. PMI.
  3. Project Management Institute. (2021). PMP Examination Content Outline. https://www.pmi.org/certifications/project-management-pmp/earn-the-pmp/pmp-exam-preparation
  4. Heldman, K. (2021). PMP Project Management Professional Exam Cram. Pearson IT Certification.
  5. Phillips, J. (2021). PMP Project Management Professional Study Guide, Fifth Edition. McGraw-Hill Education.
  6. Mulcahy, R. (2018). PMP Exam Prep. RMC Publications.